sample / scheduling
the sample project
a forecast as of 24 nov 2026, 14:05, from 10,000 simulated runs.
about 7 in 10 chance we finish by mon 14 december.
about as likely before 10 december as after.
a safe date to promise: fri 18 december.
the dates
- likely: thu 10 december
- even odds: half the runs finish by here
- 85% line: wed 16 december
- the workspace's confidence line: the headline
- safe to promise: fri 18 december
- nineteen runs in twenty finish by here
the committed date
a 72% chance of making 14 december.
filled dots finish by it. hollow dots finish after, which is a run that lands later, nothing more.
what matters most to the date
activities, never people.
- fix what they find, on the longest path in 100% of runs
- write the booking api, on the longest path in 84% of runs
- try it with five customers, on the longest path in 100% of runs
send the forecast, not a date
in the product a lead makes a share link and pastes one sentence. whoever opens the link sees a page like this one, with no sign-in.
our forecast: 85% chance by wed 16 december, likely around 10 december. live view: jollygig.com/f/…
the project, as estimated
best plausible, most likely and worst plausible, in workdays. the forecast draws a length for each, ten thousand times.
write the booking api
3 / 5 / 10 workdays
design the new booking flow
2 / 4 / 8 workdays
build the calendar view
4 / 7 / 15 workdays · after write the booking api and design the new booking flow
connect the payment provider
3 / 6 / 20 workdays · after write the booking api
move the existing bookings over
2 / 4 / 9 workdays · after write the booking api
try it with five customers
3 / 5 / 8 workdays · after build the calendar view and connect the payment provider
fix what they find
3 / 6 / 14 workdays · after try it with five customers
launch
1 / 2 / 4 workdays · after move the existing bookings over and fix what they find